The following information is from the feedback of Raji Gaspro Uganda Ltd: The a process say land also has its own paper work to transfer land from sellers name to buyers nameIt can take 1 to 3 mon...
Rated 4.5/5 based on 414 customer reviews
Share:
Content

The following information is from the feedback of Raji Gaspro Uganda Ltd:

  • The a process say land also has its own paper work to transfer land from sellers name to buyers nameIt can take 1 to 3 months depending on where you wld have purchased.
  • Then you will need geotrchnical report thts for soil sampling it will tak 1 month to get that; Then nema consultant will visit site take photos and talk with local community about the impact of the project in there area
  • So you will wait for 2 weeks to 4 weeks to get the said report from nema consultant then you submit the scoping report and terms of reference to nema  and wait for approval; Which normally take 6months to 8months to get nema certificate becoz of alot of beaucracy at govt agencies.
  • After getting that then you attache all the requirmnts as give by ministry of energy and submit and also wait , For i dnt kno some time few months so it depends if you have people who can run the things quit faster for you.Now me am on the last stage i submitted to energy ministry so am waiting.