1 After receiving the notice of liquid inflow, make preparations according to the unloading and compressor operating procedures.

 

2 Open the liquid phase inlet valve of the storage tank that needs to be fed to connect with the liquid phase pipe of the tanker, open the gas phase valve of the corresponding storage tank and connect it to the inlet of the compressor, and connect the gas phase of the tanker to the outlet of the compressor.

 

3 During the filling process, it should be noted that the pressure of the storage tank does not exceed 1.8MPA, and the liquid level does not exceed 85%. Overfilling is strictly prohibited. If overfilling is found, pour the tank immediately.